No sooner had the Alishan Forest Railway started operating than it was closed again. The historical railway was fully opened earlier this month after 15 years of arduous repairs, but after just 17 days of operation, it is suspended due to downed trees and landslides caused by Typhoon Gaemi. Authorities have announced that operations would be suspended until the end of August.
Chou Hen-kai
Alishan Forest Railway & Cultural Heritage Office
The strong winds and abundant rainfall brought by Typhoon Gaemi had caused landslides and fallen trees at 89 places along the Alishan Forest Railway, but there haven’t been any major disasters. Our office will continue to conduct route inspections, as well as cleanup and repair work as weather allows. Since most of the damaged areas are inaccessible by road, repairs need to be carried out section by section, and intermittent heavy rains have hampered the progress. We estimate that it will be completed at the end of August.
The crew inspecting the forest railway came upon a large area of earth and rocks covering the track. Elsewhere they found a tree trunk sitting in the middle of the track. Such scenes of damage can be found throughout the Alishan Forest Railway.
For more Taiwan news, tune in:
Sun to Fri at 9:30 pm on Channel 152
Tue to Sat at 1 am on Channel 53
睽違15年,阿里山林鐵在7月6日才又再度全線通車,沒想到短短營運17天,就因為這次的凱米颱風,挾帶豐沛雨量,導致路線上出現樹倒及土石崩塌等狀況,林鐵宣布,全線到8月底前都暫停營運。
[[阿里山林鐵及文資處副處長 周恆凱]]
“凱米颱風帶來的強風豪雨,已經造成阿里山林鐵沿線,邊坡土石崩落及倒樹至少89處,尚無重大災害,本處持續在天候許可下,持續進行路線巡檢及清理修復作業。因為大部分災損地點無道路可達,需逐段推進施工,且有間歇性大雨影響修復進度,預估在八月底才能完成”
工作人員沿著森林鐵路,一路巡查,就看到一大片土石掩沒在鐵道上面,還混雜著樹木殘枝,或是整根樹幹倒在路中央,像這樣的景象,幾乎遍佈整個阿里山森林鐵道沿線。
更多新聞內容,請鎖定:
民視台灣台(152頻道)週日至週五晚上9:30
民視新聞台(53頻道)週二至週六凌晨1:00